Report review · ENPG · IFRS for 2025
En+ 2025: the hydropower plants earned more on low water, aluminium went into the red, and interest ate the rest
En+ is Rusal plus Siberian hydropower plants, and in 2025 the two halves went separate ways: the power plants earned more in a year of low water, while Rusal sold 16% more aluminium and still slid into a loss. Add interest on debt, a strong ruble and tax, and the group's net profit shrank to $235 million from $1.35 billion a year earlier. We read the 93 pages of the statements, the 153 pages of the annual report and the press release, and took the year apart line by line.
2024: ₽1.36T
2024: ₽140B
2024: ₽125B
2024: ₽154B
2024: −₽20.4B
2024: ₽903B
2024: ₽191B
In short
- Revenue grew 20.8% to $17.7 billion: 16.4% more aluminium was sold — some of it from old stockpiles — at prices 5.2% higher press release, p. 1 press release, p. 8. In rubles the growth is more modest, +8.5%: the ruble strengthened over the year.
- Profit fell 82.6% to $235 million. Costs grew faster than revenue, interest on debt rose by $346 million, a $221 million exchange gain turned into a $281 million loss, and tax took 72% of pre-tax profit press release, p. 2 annual report, p. 26 statements, p. 32.
- The halves parted ways: power earned $720 million of net profit, while metals, that is Rusal, lost $455 million statements, p. 23. Yet En+'s shareholders are entitled to $428 million — more than the group earned as a whole statements, p. 9.
- Debt grew by a quarter: net debt is $11.1 billion, about four times annual EBITDA (our calculation) press release, p. 2. Within a year $9.5 billion of debt has to be repaid or refinanced, with $2.1 billion in the bank statements, p. 11.
- There were no dividends in either 2024 or 2025, although the dividend policy sets a minimum of $250 million a year statements, p. 65 annual report, p. 90.
- The auditor signed without qualifications, but, as a year earlier, with a section on material uncertainty: sanctions and the markets cast doubt on the group's ability to continue as a going concern statements, p. 5 2024 statements, p. 4.
Better or worse?
The short answer: worse. Sales went up, earnings went noticeably down. Of the nine key figures in the table, four got better and five got worse — and everything to do with profit got worse: operating and net profit, both margins, return on equity.
The table has to be read with the currency in mind. En+'s net debt grew 25.1% over the year press release, p. 2, yet in the table it “fell” by 3.8%. The reason: the company reports in dollars, while the site shows rubles at the Bank of Russia rate — the year's average for revenue, profit and cash flows, the 31 December rate for debt and the balance sheet. The ruble strengthened in 2025: on average the dollar cost 83.2 rubles against 92.7, and at year end 78.2 against 101.7. So in rubles the earnings look more modest — revenue grew only 8.5%, against 20.8% in dollars — and the debt looks smaller. One of the four green marks is the exchange rate's doing, not the company's.
The other two come with a catch. Almost twice as much cash came in from operations, but mainly because the company was selling off inventories and taking advance payments from customers statements, p. 12. And the “free cash flow” in the table leaves out interest: with interest counted, by the company's own calculation, it was negative for the second year running annual report, p. 25.
Better: 4, worse: 5, no change: 0 (of 9 figures)
| Figure | 2025 | 2024 | Change | It got |
|---|---|---|---|---|
| Revenue | ₽1.47T | ₽1.36T | +8.5% | better |
| Operating profit | ₽118B | ₽140B | −15.7% | worse |
| Net profit | ₽19.6B | ₽125B | −84.3% | worse |
| Operating cash flow | ₽245B | ₽154B | +59.8% | better |
| Free cash flow | ₽63.9B | −₽20.4B | +₽84.3B | better |
| Net debt | ₽869B | ₽903B | −3.8% | better |
| Operating margin | 8.0% | 10.3% | −2.3 pp | worse |
| Net margin | 1.3% | 9.2% | −7.9 pp | worse |
| Return on equity (ROE) | 1.7% | 10.9% | −9.2 pp | worse |
Compared with 2024 as the same report restates it. "Better" or "worse" is a rule, not an opinion: an amount moved by more than 2%, a ratio by more than 0.5 percentage points; for debt, less is better. Net profit here is the whole profit of the group for the year; the part attributable to the shareholders of En+ is ₽35.6B (−61.4% against 2024).
Where a billion dollars of profit went
Let's walk from the 2024 profit to the 2025 profit along the lines of the statements. The chart shows the steps in rubles, at each year's average rate; the text uses dollars, as the report does. Over the year profit fell from $1,348 million to $235 million statements, p. 9.
Revenue added $3.05 billion, but operating expenses grew by $3.48 billion; that is our calculation from the lines of the statements statements, p. 9. The cost of sales rose 29.7%: more metal was sold, and raw materials got dearer — petroleum coke by 21.8%, anode blocks by 9.9% press release, p. 1 press release, p. 8. In the end gross profit barely moved: $4.46 billion against $4.43 billion statements, p. 9. Everything else was decided further down — in interest, the exchange rate and tax.
Why is the tax so big when the profit is so small? Each company in the group pays tax on its own. The power business, with pre-tax profit of $1.11 billion, handed over $393 million, while metals, despite a pre-tax loss of $239 million, still booked $216 million of tax statements, p. 23. Another $180 million is tax assets the group chose not to recognise in its statements statements, p. 32.
And about the exchange rate. For a company that counts in dollars, a strong ruble is bad news: its ruble costs and ruble debts become more expensive in dollars. The company itself names the stronger ruble and tight monetary policy, which made loans and bonds more expensive, as the main reasons profit fell press release, p. 3.
Where the money goes
Of every ₽100 of revenue in 2025, En+ spent ₽92.0 on costs and expenses; ₽3.4 went to income tax, ₽3.2 went to interest and other items, and ₽1.3 was left as net profit.
In 2025, En+ took in ₽245B of cash from its operations. Of every ₽100 of it, it spent ₽74.0 on capital expenditure. The remaining ₽26.0 was left for other uses: repaying debt, investments or the cash balance.
| In 2025 | Amount | Of revenue |
|---|---|---|
| Revenue | ₽1.47T | 100.0% |
| Costs and expenses | −₽1.36T | 92.0% |
| Operating profit | ₽118B | 8.0% |
| Income tax | −₽50.3B | 3.4% |
| Interest and other, net | −₽47.8B | 3.2% |
| Net profit | ₽19.6B | 1.3% |
| In 2025 | Amount | Of operating cash |
|---|---|---|
| Operating cash flow | ₽245B | 100.0% |
| Capital expenditure | −₽182B | 74.0% |
| Free cash flow | ₽63.9B | 26.0% |
| Left over | ₽63.9B | 26.0% |
The business: the hydropower plants had less water but more money, Rusal the other way round
En+ is two companies under one roof. Metals means Rusal, in which En+ holds 56.88% statements, p. 93; it accounts for 83% of the group's revenue from outside customers (our calculation) statements, p. 23. Power means the hydropower plants of the Angara and Yenisei cascades, coal-fired heat and power plants and open-pit coal mines, mostly in Eastern Siberia statements, p. 16 press release, p. 5. Rusal gets a detailed review of its own; here is what matters for En+.
Power had a paradoxical year. The Angara cascade's hydropower plants generated 19.8% less: the company puts this down to lower water reserves in Lake Baikal and the Bratsk Reservoir and to the discharge regime set by the basin water authority press release, p. 5. But low water and expensive coal pushed prices up: on the day-ahead market in Siberia a megawatt-hour became 25.3% dearer, in the Irkutsk region 31.7% press release, p. 6. EBITDA of the hydropower plants (profit before interest, taxes and depreciation) grew from $1.38 billion to $1.79 billion annual report, p. 32, and net profit of the power business from $553 million to $720 million press release, p. 4.
Metals sold more and earned less. Aluminium output fell 1.9%, while sales rose 16.4% — the company was selling off stocks built up in earlier years press release, p. 9 press release, p. 8. The exchange price rose 8.7%, but the premium on top of it halved, from $157 to $76 a tonne press release, p. 9. Metals EBITDA fell 29.5% to $1.05 billion, and the net result was a $455 million loss press release, p. 7.
There is a link between the halves that is easy to miss: Rusal is the main buyer of electricity from En+'s hydropower plants press release, p. 12. Inside the group, power sold metals $1.81 billion worth against $1.09 billion a year earlier statements, p. 23 statements, p. 25. For the group this is money moving from one pocket to another, but not for shareholders: 43.1% of Rusal's loss falls on its other co-owners statements, p. 66. That is why En+'s shareholders are entitled to $428 million of profit — more than the whole group earned, $235 million statements, p. 9.
Who earned it: metals against power
What was sold: revenue from outside customers by product
The year in tonnes and kilowatt-hours. The whole group's output fell 9.6% to 82 billion kWh, almost entirely because of the Angara; the Krasnoyarsk hydropower plant on the Yenisei, on the contrary, generated 13.7% more press release, p. 5. In metals, 16.2% more bauxite was mined, as the mines in Guinea expanded their capacity, and 6.7% more alumina was produced, mainly thanks to stakes in Chinese and Indian refineries press release, p. 9 annual report, p. 20. The group covers about 85% of its needs with its own alumina; the goal is at least 100% annual report, p. 10 annual report, p. 14.
| Operating figure | 2025 | 2024 | Change | Where in the report |
|---|---|---|---|---|
| Electricity generationTWh | 82.0 | 90.7 | −9.6% | press release, p. 5 |
| of which hydroTWh | 65.3 | 73.7 | −11.4% | press release, p. 5 |
| Angara cascadeTWh | 44.5 | 55.5 | −19.8% | press release, p. 5 |
| Day-ahead power price, Siberia (2nd price zone)rubles per MWh | 1,895 | 1,512 | +25.3% | press release, p. 5 |
| Aluminium productionthousand tonnes | 3,918 | 3,992 | −1.9% | press release, p. 9 |
| Aluminium salesthousand tonnes | 4,490 | 3,859 | +16.4% | press release, p. 9 |
| Aluminium price on the LMEUS dollars a tonne | 2,630 | 2,419 | +8.7% | press release, p. 9 |
| Premium over the LME priceUS dollars a tonne | 76 | 157 | −51.6% | press release, p. 9 |
| Alumina productionthousand tonnes | 6,858 | 6,430 | +6.7% | press release, p. 9 |
| Bauxite outputthousand tonnes | 18,453 | 15,885 | +16.2% | press release, p. 9 |
Cash: stocks sold off, the gap borrowed
Almost twice as much cash came in from operations: $2.95 billion against $1.66 billion statements, p. 12. But the earnings themselves, before changes in working capital, fell: $2.82 billion against $3.02 billion. The difference came from the warehouse and from customers: inventories shrank in 2025 after growing by $847 million a year earlier, and advances received rose from $544 million to $1.18 billion statements, p. 12 statements, p. 11. This is one-off money: a warehouse cannot be sold off for ever.
Construction and equipment took $2.18 billion, 16.2% more. The power business has started building new capacity under the state's competitive selection of new generation, and metals is spending on the environmental upgrading of its smelters press release, p. 3. But interest does not get into the “free cash flow” on the card: En+ shows it in the financing section, and it paid $1.44 billion of interest against $929 million a year earlier statements, p. 13. Leaving interest out, $768 million remains after construction (our calculation). By the company's own method, free cash flow was minus $397 million, after minus $547 million in 2024 annual report, p. 25.
2024: ₽154B
2024: ₽174B
2024: −₽20.4B · operating cash flow minus capital expenditure
2024: ₽903B · borrowings minus cash
2024: ₽191B
Where the cash went
The hole was plugged with debt. Over the year the group borrowed $10.94 billion and repaid $10.26 billion — refinancing more than three quarters of its debt (our calculation) statements, p. 13 statements, p. 24. And it refinanced at a higher price: yuan bonds at 3.75% were repaid, while the new yuan issues of Rusal and the power business were placed at 12% statements, p. 69 statements, p. 70.
Net debt rose to $11.1 billion from $8.88 billion: $8.05 billion in metals and $3.06 billion in power press release, p. 1. That is about 4.1 times annual EBITDA against 3.0 a year earlier (our calculation). The company explains the increase by the strong ruble and the start of big construction projects press release, p. 3. On the ruble card the debt “slimmed down” by 3.8% only because the dollar cost 78.2 rubles on 31 December, not 101.7.
The main risk is timing. Short-term debt rose from $5.78 billion to $9.5 billion, and current liabilities exceed current assets by $3.7 billion (our calculation) statements, p. 11. Under its contracts the group has to pay $11.87 billion on its debts and bills within a year, and it has $2.11 billion in the bank statements, p. 86 statements, p. 11. The group is in compliance with its loan covenants statements, p. 68. There is a safety margin, but not in cash: the Nornickel stake is worth $7.69 billion on the stock exchange statements, p. 57. Then again, 25% plus one share of Nornickel is pledged against Rusal's loans statements, p. 69.
Against its own history
One year is easily mistaken for a trend, so let us look at the series since 2016 (2019 is missing from our data). In rubles, 2025 revenue is the highest in the series, ₽1.47 trillion. Net profit, ₽19.6 billion, is the lowest: even in 2023 it was three times as large.
The cards show six ratios. Three are at a record for the series, and all three are bad ones: a net margin of 1.3%, return on equity of 1.7% and a tax rate of 72%. The operating margin, 8.0%, is near the bottom of the range. Capital expenditure takes 12.3% of revenue — more than is usual for the company. On the other hand, net debt to equity, at 79%, is below the middle of past years, around 123%.
Median of the earlier years: 12.1% (years counted: 9). Number 9 of 10 by size.
Median of the earlier years: 11.2% (years counted: 9). Number 10 of 10 by size.
Median of the earlier years: 18.3% (years counted: 8). Number 9 of 9 by size.
Median of the earlier years: 138.4% (years counted: 9). Number 8 of 10 by size.
Median of the earlier years: 9.6% (years counted: 9). Number 2 of 10 by size.
Median of the earlier years: 17.5% (years counted: 9). Number 1 of 10 by size.
One bar is one year, the latest in color; the dashed line is the median of the earlier years. Years before the latest two are as first published.
Among Russian metals and mining companies: the biggest revenue, one of the lowest margins
The comparison covers seven Moscow Exchange companies whose IFRS reports for 2025 we have. By revenue En+ is the largest: ₽1.47 trillion, more than Nornickel with its ₽1.15 trillion. By margin it is near the tail: an operating margin of 8.0% against 29% at Nornickel, 59% at Polyus and 14% at Alrosa; only Rusal (0.9%) and Raspadskaya (minus 52%) are lower.
The En+ and Rusal pair says more than the whole table. Rusal sits inside En+ and ended the year with a loss of ₽37.9 billion. En+ ended it with a profit of ₽19.6 billion. The difference came from power.
Net profit grew at Nornickel (+22%), Polyus (+3%), Alrosa (+88%) and UGC (+81%). At En+ it fell 84% — the worst result among those that stayed in the black; Rusal, Seligdar and Raspadskaya ended the year with losses.
Calculated by BigCapital from the companies' IFRS statements for 2025; a change is against the year before as the same report shows it. ROE: profit for the year over the average of equity at the start and the end of the year.
Among the world's miners
Direct counterparts — aluminium plus hydropower plants of its own — are not in our world sample: it consists of the largest mining companies, from their reports to the US securities regulator. Here, though, the exchange rate does not get in the way: En+ itself counts in dollars.
With revenue of $17.7 billion, En+ is the smallest of the five: Newmont has $22.7 billion, Rio Tinto $57.6 billion. In revenue growth (+20.8%) it is level with Newmont (+21.3%) and far ahead of Rio Tinto, Vale and Freeport-McMoRan, which grew by 1% to 7%.
By profit it comes last: $235 million and a net margin of 1.3%, against 5.2% at Vale and 31.3% at Newmont.
En+: in rubles; in dollars at the year's average rate, +20.8%.
Foreign companies: their annual reports to the U.S. Securities and Exchange Commission (Forms 10-K and 20-F), SEC EDGAR. Rubles are converted at the Bank of Russia's average official rate: 83.21 rubles per dollar in 2025, 92.66 in 2024.
What the auditor said
The auditor found no errors in the figures: the statements present the group's position fairly “in all material respects” statements, p. 4. But the report has a separate section, “Material uncertainty related to going concern”. Sanctions, geopolitics and swings in commodity, stock and currency markets could seriously affect the group's operations, and this may cast significant doubt on its ability to continue as a going concern statements, p. 5.
In plain words: this is a warning, not an accusation, and it is not new — the same section was in the report on 2024, signed by the same firm under its former name 2024 statements, p. 4. The company itself writes of a “material uncertainty” about its ability to meet its financial obligations on time and is counting on higher commodity prices statements, p. 17. What is new in 2025 is the figures alongside: short-term debt of $9.5 billion, and current assets smaller than current liabilities statements, p. 11.
Key audit matters: what the auditor looked at most closely
- Impairment of property, plant and equipmentThe only key audit matter. Aluminium prices, premiums, the cost of bauxite, alumina and coal, and logistics may mean new write-downs as well as the reversal of old ones. The auditor compared the assumptions in the models with published forecasts and checked how accurate management's past forecasts had turned out to be statements, p. 5 statements, p. 6.
Taishet shows how fragile these estimates are: if the aluminium price were 5% below the forecast, the smelter and the anode plant would have to be written down by another $236 million statements, p. 42. And the coal-fired heat and power plants passed the test on the assumption that the prices of their electricity will rise by 42–77% by 2035, and heat tariffs by 74% statements, p. 43.
The auditor had not seen the annual report by the time of signing, and the opinion does not cover it statements, p. 6.
The year's main events
What happened during the year and right after it — from the company's documents.
- 4–7 March 2025Rusal placed ₽30 billion of bonds with a coupon of “key rate + 3.7%” and repaid 8.9 billion yuan of bonds at 3.75% statements, p. 69.
- 16 and 23 May 2025Rusal and the power segment placed yuan bonds of 11.2 billion and 4.6 billion yuan on the Moscow Exchange — both issues at 12% a year statements, p. 70.
- 21 May and 25 June 2025The board of directors proposed, and the shareholders' meeting decided, not to pay dividends for 2024 annual report, p. 90.
- July 2025A 26% stake in India's Pioneer Aluminium, an alumina refinery with a capacity of 1.5 million tonnes, was bought for $246 million; the stake can be raised to 50% statements, p. 58.
- 24 September 2025The stake in Bogatyr Coal in Kazakhstan fell from 50% to 35% annual report, p. 19.
- 202531.9 million of En+'s own shares (about 5% of the capital, our calculation) were donated; to whom, the statements do not say statements, p. 65.
- 2025The Taishet aluminium smelter produced 393,000 tonnes — 92% of capacity annual report, p. 20.
- 2025A positive state expert review and a construction permit were obtained for the new units of CHP-11 annual report, p. 35.
- 2025An agreement was signed with Buryatia and the Far East and Arctic Development Corporation on the future construction of the Mokskaya hydropower plant annual report, p. 35.
- 19 March 2026The board of directors approved the 2025 statements, and the auditor signed its report statements, p. 3 statements, p. 8.
- 2026, after the reporting dateConstruction began on three units at CHP-11 with a capacity of 690 MW; the Zabaikalskaya thermal power plant of about 1 GW will be built under the state's selection programme for new generation annual report, p. 7.
Promised — delivered?
We took En+'s annual report for 2024, wrote out the promises with a number, a date or a specific project, and checked them against the 2025 documents. Reports for earlier years are not in our set, so the record of promises here is short.
A caveat: many of En+'s goals are construction projects with a 2026–2031 horizon, and for now they can only be checked by the progress of the work.
The picture is this. What depends on engineers — Taishet, the CHP plants, the hydropower upgrades — is moving, if more expensively and more slowly than promised. Promises to shareholders and creditors fare worse: instead of falling, debt grew by a quarter, and there are no dividends despite a “minimum” of $250 million a year. And there are quiet disappearances: the wind farm, described with figures a year ago, has simply vanished from the report.
What the company itself writes
En+'s Consolidated Report for 2025 runs to 153 pages in English, with a 12-page press release alongside. Here is their content in six points.
- The main idea: En+ “demonstrates operational stability” despite external pressure — that is how CEO Vladimir Kolmogorov described the year press release, p. 2.
- External conditions are to blame: currency swings, expensive loans, dearer equipment and sanctions; moderate growth in aluminium demand only partly softened the blow press release, p. 1 annual report, p. 12.
- A bet on construction: more than 1.7 GW of new generating capacity in Siberia and Transbaikalia — CHP-11 and the Zabaikalskaya thermal power plant; in the CEO's words, the money goes into projects “with confirmed economics and guaranteed returns” annual report, p. 12.
- Scale: Christopher Burnham, chairman of the board, calls En+ the world's largest non-government-owned hydropower company — more than 80 billion kWh a year and heat for half a million homes in Siberia annual report, p. 11.
- Water is the main risk for power: the company has developed a new method of forecasting the water inflow to the Irkutsk hydropower plant and writes at length about the levels of Lake Baikal and the reservoirs annual report, p. 11 press release, p. 5.
- Raw materials of its own: 26% of India's Pioneer alumina refinery in 2025 and 30% of China's Hebei Wenfeng a year earlier — steps towards the goal of supplying all its own alumina press release, p. 1 annual report, p. 14.
What the report is silent about
- Debt to EBITDA: neither the annual report nor the press release gives it. By our calculation it is about 4.1 for the group and about 7.6 for metals.
- The decision on dividends for 2025: the documents contain no board recommendation annual report, p. 90.
- A forecast for 2026: no output, EBITDA or capital expenditure figures — only projects and dates.
- The doubt about the ability to meet obligations is stated in the financial section of the report, but not in the letters from the chairman and the CEO annual report, p. 33 annual report, p. 11 annual report, p. 12.
- The wind farm from last year's report: not a word 2024 report, p. 37.
- Who received the 31.9 million own shares that were given away statements, p. 65.
What we will check in a year
Here is what we can come back to when the report for 2026 is out.
| What is promised | Due |
|---|---|
| Repay or refinance $9.5 billion of short-term debt with $2.1 billion in the bank statements, p. 11 | 2026 |
| Dividends: under the policy, at least $250 million a year annual report, p. 90 | for 2025 |
| “New Energy”: more than 2.4 billion kWh of extra hydropower output a year annual report, p. 35 | from 2026 |
| Taishet anode plant: the first phase at design capacity, the start of construction of the second annual report, p. 34 | 2026 |
| CHP-11: three units with 690 MW on a budget of up to ₽250 billion; capacity supply to start on 31 December 2028 and 1 July 2029 annual report, p. 35 2024 report, p. 36 | 2028–2029 |
| The 1,050 MW Zabaikalskaya thermal power plant, with financing of up to $5.1 billion annual report, p. 35 | no date given |
Sources and how we counted
The original documents are on the disclosure site; we do not copy them, we link to them:
- En+ Group: IFRS consolidated financial statements for 2025 with the auditor's report (in Russian) — 93 pages
- En+ Group: IFRS consolidated financial statements for 2024 with the auditor's report (in Russian) — 90 pages
- En+ Group: Consolidated Report 2025 (in English) — 153 pages
- En+ Group: FY2025 financial and operating results, press release (in English) — 12 pages
- En+ Group: Annual Report 2024 (in Russian) — 160 pages
- The figures are taken from the company's statements; a comparison with the year before uses the prior-year column of the same report, so the company's own restatements are already in.
- Margins, return on equity, free cash flow and net debt are calculated by BigCapital from those figures. Net debt here is borrowings minus cash; the company has its own method, and its figure is shown separately. En+ reports in US dollars; on this page its figures are converted to rubles at the Bank of Russia's official rate: the year's average for revenue, profit, cash flows and per-share figures, the last rate of the year for the balance sheet. The original documents show the figures in US dollars.
- The reasons for the changes come only from the company's documents; each has its page (page numbers are those of the PDF file). Where a report names no reason, we say so.
- The "better" and "worse" marks are arithmetic by one rule, not an opinion, and not advice to buy or sell shares.
- Peers: Russian companies by their IFRS statements for the same year, world companies by their reports to the SEC.
En+: every year — revenue, profit, balance sheet
For information only, not investment advice.
The charts could not be loaded; the table below has the same numbers.